Sistema Pontarolo – Construction of Mainardis pharmacy in San Vito al Tagliamento

https://pontarolo.com/wp-content/uploads/2021/01/IMG_0284.jpg
https://pontarolo.com/wp-content/uploads/2021/01/IMG_0334.jpg
https://pontarolo.com/wp-content/uploads/2021/01/IMG_0325.jpg
https://pontarolo.com/wp-content/uploads/2021/01/IMG_0381.jpg
https://pontarolo.com/wp-content/uploads/2021/01/s11.jpg
https://pontarolo.com/wp-content/uploads/2021/01/s12.jpg
https://pontarolo.com/wp-content/uploads/2021/01/IMG_0432.jpg
https://pontarolo.com/wp-content/uploads/2021/01/IMG_0880.jpg
https://pontarolo.com/wp-content/uploads/2021/01/IMG_0888-min-scaled.jpg
https://pontarolo.com/wp-content/uploads/2021/01/IMG_0855.jpg
https://pontarolo.com/wp-content/uploads/2021/01/s1.jpg
https://pontarolo.com/wp-content/uploads/2021/01/s6.jpg
https://pontarolo.com/wp-content/uploads/2021/01/s2.jpg

Sistema Pontarolo – Construction of Mainardis pharmacy in San Vito al Tagliamento

Title:

Description:

Construction of the new headquarters of the Mainardis Pharmacy in San Vito al Tagliamento, using the Climablock formwork, Isolcupolex and Spyrogrip raised slab. Thanks to the use of the Pontarolo System, the roof was completed just over 10 weeks after the start of the demolitions and after only 6 months the Pharmacy was open to the public.

➡️ Very fast construction

➡️ healty and comfortable building

➡️ Antiseismic

➡️ High thermal insulation

Year
2019
City
San Vito al Tagliamento
Technology
Climablock, Isolcupolex, Spyrogrip